04/24/06 |
THIS PROJECT IS
A METRA PROJECT
My office contacted Christopher Burke Engineering, the
engineer for the County of Cook. We were advised that
the standing water is the result of a broken drain tile
which will be temporarily repaired until the construction
of 108th Avenue is completed. This project is schedule
to begin this summer and to be completed next year. At
that time, a permanent solution will be implemented. |
06/26/06 |
THIS PROJECT IS A METRA PROJECT
The Cook County Highway Department has let this project
out for bid. Bids should be recieved by July 28. At that
time, we will have a better idea as to when the project
will begin and how long it will take. Keep checking back
for more information. |
10/25/06 |
THIS PROJECT IS A METRA PROJECT
108th Ave will be closed to all traffic
beginning October 30th until
November 23rd when it will be opened for one lane of traffic
with flaggers. The one lane closure will last until approximately
December 25th when the road will be fully opened until
Spring 2007.
The scope of the work being done this fall is drainage
work at the north end of the road to alleviate flooding
issues and the construction of a retaining wall approximately
300 ft. south of Jillian on the west side of the street. |
10/26/06 |
THIS PROJECT IS A METRA PROJECT
When the road closes, detour signs will be posted to
assist Ashburn Sound residents with access to the subdivision.
Click here for the detour routes. |
12/10/06 |
THIS PROJECT IS A METRA PROJECT
108th Avenue has been opened for travel since November
23, 2006. It will not be closed down again until sometime
in spring.
Currently, the issue of flooding at the north end of
108th Ave. has been fixed and should not flood again. |
3/29/07 |
THIS PROJECT IS A METRA PROJECT
108th Avenue will again be closed beginning April 2,
2007 to all traffic for approximately six weeks. The same
detour route will apply as did in the fall of last year.
Click here for the detour routes. |
6/6/07 |
THIS PROJECT IS A METRA PROJECT
108th Avenue will be closed between Jillian Rd. and 159th
Street beginning on June 11, 2007. The road will re-open
between Jillian and 153rd St. at that time. On June 22nd,
2007 it will open between Somer Glen and 153rd. |
09/10/07 |
THIS PROJECT IS A METRA PROJECT
METRA has been experiencing delays related to Commonwealth
Edison and the utility easements on 108th Ave. The delays
have been worked out and Commonwealth Edison has given
METRA a completion date of September 11 as the target
completion date for their work. Once they have moved their
utility poles, the work will begin again. The compeltion
date for 108th Avenue is mid to end of December 2007.
At that time, the road will be completely opened between
143rd and 159th St. |
6/10/08 |
The construction project has been moving along and will
be completed by August. |